By RAELYNN RICARTE
News staff writer
August 29, 2007
Hood River downtown business owners drafted
up a plan last week that could help them survive economically
during an upcoming construction project.
High on the list was a request that Oak
Street remain open to traffic on Valentine’s Day. Contractors
will begin working along Oak between Third and Fifth streets by
the second week of February. But some retailers are worried
about losing profits on a day that traditionally yields high
sales.
“On a personal note, just so you know, Feb.
14 is the biggest day of my life,” said Lucy Gorman, owner of
Lucy’s Informal Flowers.
Other business owners were equally concerned
about having Urban Renewal improvements extend past the start of
the tourist season in late May.
“There’s pressure on both sides, so it’s a
tough one,” said Lindsay Gott, owner of South Bank Kitchen.
About 25 retailers gathered at Dog River
Coffee Company on Aug. 23 to voice concerns. The meeting was
facilitated by Moira Reynolds, Downtown Business Association
coordinator. She had requested that Ki Bealey from Wallis
Engineering, the firm based in Vancouver, Wash, that will
oversee the work, and Bob Francis, city manager, be present to
answer questions.
“I think we all understand how lucky we are
that the city is taking us into this project. We can’t say
‘thank you’ enough,” said Reynolds.
Next winter, the city will undertake the
final phase of Urban Renewal work that began in the late 1990s.
The $1.2 million project includes replacing aging water, sewer
and stormwater lines along a two-block section of Oak. In
addition, new sidewalks will be poured and ornamental trees
planted.
The stretch of Fourth Street from Oak to
State Street will also be closed at times to accommodate the
undergrounding of utilities.
DBA members want signs posted that alert
customers to the fact that, while sections of Oak are closed,
stores are open In addition, the DBA plans to launch an
advertising campaign that will deliver the same message via
media outlets.
Francis said pedestrian access will be
provided through the work zone. He and Bealey agreed that
contractor and subcontractors could be required to park off-site
so that spaces on or near Oak would be accessible to customers.
Bealey said entry into businesses would be
blocked while the repaving of Oak was underway. However, he said
that stage of the project could be planned for the middle of the
week when business was slower.
“It’s going to be painful, no doubt. But we
are here to talk with you and see how we can make it a little
more painless,” he said.
Francis also agreed to scout out the
possibility of reserving parking spaces in the city lot on
Cascade Avenue to accommodate the loading and unloading of
merchandise.
“The city is going to do everything that it
possibly can do to make this a little easier for you,” he said.
For example, he said the work had been
scheduled for a time of year when there were fewer visitors
coming through town.
In addition, an incentive and/or penalty
clause would be written into the work contract. Francis believes
the possibility of a reward or a sanction will ensure that
infrastructure upgrades and beautification of Oak was completed
on schedule.
He and Bealey said overtime costs would be too high to
accommodate a DBA suggestion that construction take place only
at night. They also said it would likely prove unaffordable to
have crews on the job 24 hours a day in order to shorten the
time frame for the work.