By SUE RYAN
News staff writer
October 15, 2007
A steady thudding sound and disembodied voice
can be heard just offshore of Bradford Island near Bonneville
Dam.
The sounds are not the accompanying
soundtrack to a horror flick but the work of underwater divers
as they vacuum the Columbia’s riverbed and talk over a speaker
to their crew above water.
The contract crew from Huang Associates and
Co. from Elk Grove, Calif., began work Oct. 1. They are working
under a $1.9 million contract with the U.S. Army Corps of
Engineers and are expected to be finished by Nov. 15.
To work outside of the normal window of
allowed in-water work, the agency collaborated with several
other federal agencies that oversee fisheries management in the
Columbia River.
“I don’t know of another project in my 20
years where we have gotten the cooperation we have on this
project to work outside of the window,” said Mark Dasso, the
Army Corps project manager.
Generally in-water work is only allowed
between Dec. 1 and Feb. 28, which is outside of the time span
fish migrate through the Columbia River.
While a two-year study is still underway to
evaluate the extent of the remaining contamination on the island
and in the river, the Corps wanted to be proactive in removing
what it already knew to be polychlorinated biphenyl (PCB) laced
sediments.
The contamination is concentrated in the
river bottom sediments on the north side of Bradford Island and
includes a .83-acre area of “hot spots.”
The Corps took the action after the
recommendation of a citizens’ advisory group, which included
Rachael Pecore of Columbia Riverkeeper and Cascade Locks City
Councilor Darrell Driver.
The contamination on Bradford Island came
from several sources, which the Corps has been compiling and
studying. They have identified five upland sites: an old
landfill, old pistol range, drum storage area, sandblasting area
and slope where light bulbs were dumped.
Many of the sites remain from a time when
government workers were housed on upper Bradford Island. The
in-water site, on the lower island, is the target of the cleanup
efforts. Dasso said the Corps discovered three distinct piles of
electrical capacitors dumped in the water that came from a
former powerhouse replacement.
PCBs are colorless, odorless and tasteless
chemicals that were widely used in electrical equipment such as
transformers and capacitors before their production was banned
in 1976.
The species most at risk from the sediment
contamination are clams, smallmouth bass and crayfish.
The Corps removed the equipment in 2002 and
sampled the sediments in 2003. The cleanup on the entire project
is expected to last at least two more years.
For now, as shown in an underwater video, the
divers will nudge the hose along the bottom inch by inch. A
cylindrical grated cap barrel sits over the top of the hose to
prevent it from clogging with clam shells. To prevent the
contaminated sediment from flowing downstream, divers are
working slowly and feeding sediment directly into the hose.
“There was a concern that the cleanup might
send material downstream but this action should be taking care
of the issue,” Dasso said. “We’re measuring turbidity downstream
and those measurements have shown no changes so far.”
Once the crews vacuum up the sediment, the material goes
through a series of filters and settling tanks before the water
is returned to the river. The contaminated waste will be sampled
and then transported to an appropriate disposal facility.