By SUE RYAN
News staff writer
Debris torrents off Mount Hood more than a year
ago damaged multiple sites in Hood River County including two of
its irrigation districts and one water district.
A year later most of the repairs are completed
but all three districts face the same problem: They can’t get
flood insurance against future events.
Most are building in-house reserve accounts to
fund against future damages, which means some planned
maintenance or improvements will have to be delayed.
Middle Fork Irrigation District
MFID sits nearest the mountain, especially near
the Eliot and Coe glaciers. When debris came sloughing off the
glaciers, the damage caused the complete shutdown of three
facilities and knocked two of their five powerhouses offline.
The debris flow sent boulders, rocks and trees
down Eliot Canyon, causing more than $1 million in damages. So
far repairs have totaled $928,462. But significant additional
costs are expected for more repairs.
Initial repair work involved two weeks of
clearing debris and replacing 500 to 600 feet of 36-inch pipe.
But a year later, more repairs remain to be
finished. MFID manager Dave Compton said 1,000 feet of pipe
remains in question.
“We know it is damaged but the question is what
to do,” he said.
MFID recently received a survey of the damaged
pipe. While the line was initially buried under three to four
feet of dirt, the manufacturer’s stress rating allows it to take
pressure from being underneath eight to 10 feet of fill.
The problem is that the debris flow buried the
pipe under 24 feet of dirt and rock. Compton said it would be a
very expensive fix but because the section carries 75 percent of
the district’s water load that it must be dealt with.
“We have two options, one to excavate all 750 to
1,000 feet and figure out why the pipe has bellied down (sunk)
and re-bed it at a new level,” he said. “Or to bypass it
entirely and put another pipe across to connect at the ends of
the old section.”
Compton said the district will make sure the
line is secure by next irrigation season and will cost out
repairs this winter. While the old insurance policy for the
district will cover this repair, the district cannot get flood
insurance against future events.
Compton said the carrier has dropped the
district due to the history of catastrophic events off Mount
Hood that create expensive damages repeatedly.
“I did find some flood insurance for the dam (Laurance
Lake) but the cost is astronomical,” he said.
The district will meet with its membership on
the potential insurance in late December or early January.
Farmers Irrigation District
Water dumped boulders, debris and silt into a
600-foot section of canal along the Hood River, which sits about
midway between the MFID and Ice Fountain further downriver.
The flood tore out an additional section of 75
feet of flume wall. The damage knocked out service to 3,200 of
the 5,800 acres that FID services for 1,600 residential and
agricultural users.
The system had to be repaired to fix the
powerhouse to provide electricity as well as irrigation. Their
work first involved building two roads, one to give Pacific Corp
access to re-locate a downed power pole and a second to access
the district’s head gates.
Because the powerhouse also generated revenue,
the district was faced with the double hit of losing its ability
to make money to pay for repairs as well as serve clients.
A year later, district spokesman Jerry Bryan
said the outlook is much better.
“Insurance people said it was not covered, then
found a way to cover it,” he said.
That ended up as $2,283,000 million in repairs
at the end. Bryan said the turnaround happened with the help of
Special Districts Association of Oregon as well as FID’s acting
manager Mike Kleinsmith.
“We recovered all our expenses because FEMA paid
for all mitigation and not just repair work,” Bryan said. “That
means that FEMA paid us to build it extra stout.”
The design included making walls four times as
thick as before with a lot of steel inside. The project has been
capped with steel plates and a remote control gate added to shut
off the canal in case of a repeat event.
“What we have done is build it in a way that
will withstand future events up to the magnitude of at least the
November 2006 event,” Bryan said.
n Ice Fountain Water District
Floodwaters carrying debris continued scoured a
new path as it shot its way downstream. For the Ice Fountain
Water District, Director Mark Beam saw the river not just jump
its banks but permanently change course.
The morning of the flood, the debris slammed
into the district’s square block surrounding its spring. Before
then, the river was 50 feet away from the spring block and
behind a wall of riprap.
“It took the material down to the footing,” Beam
said.
Before that the riprap covered most of the 16
foot high structure. The problem quickly became one of potential
contamination as the river waters were threatening the footing
for the spring.
Beam shut off the transmission line, ran water
only from reservoirs and put 200 households near York Hill Road
on notice to take precautionary measures.
After purchasing water from the city for a few
days to serve lower elevation areas for some of its 2,000
customers, the district then commenced repairs. That included
having Hanel Development putting in emergency riprap barrier
followed by flushing transmission lines and chlorinating
temporarily.
The district paid about $118,000 for those
temporary measures but the permanent fix has yet to be
completed.
“We want to do permanent repairs but in order to
do it we have to be in water between July 15 and Aug. 30,” Beam
said.
The procedure requires going through a fisheries
review and permit process through the state. Beam said the
district still needs to regrout around the spring box’s footing
because of water leakage.
“The hydraulic grade of the river changed so
much we are losing water out of the spring,” he said.
In addition, Beam would like the district to be
able to cable down the riprap they put in place to keep it from
washing away during another event. He estimated those permanent
repairs at $400,000 although 75 percent will be paid for from
already approved FEMA funds.
The district has to pay the remaining 25 percent
out of pocket.
“We did not have flood insurance and we sure
can’t get it now,” Beam said.
He wanted to get the message out to all users
that the district has done all they can do and are confident the
water source is secure until permanent repairs take place next
summer.