|
|
|
By
News staff writer
A crew
armed with heavy machinery and hydraulic hammers went to work this
week on the most destructive phase of the several-months-long
Powerdale Dam decommissioning project. After
isolating the 200-foot-long diversion structure that has blocked the
While
workers from Weekly Bros. Inc. — the prime contractor PacifiCorp chose
for the roughly $2.4 million project — are busy stirring up dust at
the project’s upstream location, downstream at the powerhouse just
outside Hood River things have settled and public access to the site
has been reopened. Earlier this year a small crew and two large cranes
carefully took down, piece by piece, the tall green tower and surge
tank that took the humble honor of being the tallest structure in town
for many decades. Inside the powerhouse much of the old equipment has
been cleared out, with only the gear left to manage the transfer
station that is still in operation. “The
project has gone very well,” said Todd Olson, PaciCorp project
manager, who led a tour of the sites last week. “Everything has been
very smooth, which is important for the contractors since they are on
a pretty strict timeline.” Olson
brought a group of about 15 people on Thursday morning through the
lower powerhouse, then up to the dam site for a tour of the project’s
progress. With no significant complications to speak of, the tour was
a fairly straightforward explanation of what has been done so far,
what crews are currently doing and what is left to do in the near
future. Once the
dam is removed and the riverbed is shaped to a natural grade, the
river will be released, free to flow unrestricted for the first time
in nearly 100 years. Concrete
extended about 18 feet below the bed of the river, so a huge hole had
to be dug at the downstream side of the dam to get to the base of the
structure. The hole will have to be filled in strategically so that
over time material doesn’t wash away, leaving an unnatural section of
river or rapids. Olson
explained that the goal is to create a section of river where, once
vegetation around the project is restored, it looks and flows just
like any other part of the river. If all goes as planned, local
kayakers will not have a new set of class-4 rapids where the dam once
was.
Up and
downstream fish access has remained open throughout the project.
Currently, fish can travel downstream in either of the two side
channels used to direct the river around the dam. Upstream access has
been limited to the dam’s old fish ladder, which was used from 1923
until about 1999, when the Oregon Department of Fish and Wildlife
built an on-site facility used to regulate and count fish traveling
upstream. The facility was reduced to rubble as part of the
decommissioning project; where it once was will eventually be a
restored riparian area.
|
|
||||||||
|
|